A, installation procedures and matters needing attention: 1, open the stabilizer, remove manual and spare parts packing cases, and keep it. 2, will take, reliable machine stabilizer in dry ventilated place.
A, installation procedures and matters needing attention:
1, open the stabilizer, remove manual and spare parts packing cases, and keep it.
2, will take, reliable machine stabilizer in dry ventilated place.
3, TND, TNS series input and output wire choices:
Single phase |
Three phase | Wire section |
SVC-500VA to 1500VA | TNS-1500VA to 4500VA | 1 mm² |
SVC -2000 VA | TNS -6000VA | 2 mm² |
SVC -3000 VA | TNS -9000VA | 2.5 mm² |
SVC -5000 VA | TNS -15000VA | 4 mm² |
SVC -7500 VA | TNS -22500VA | 6 mm² |
SVC -10000 VA | TNS -30000VA | 10 mm² |
SVC -15000 VA、20000 VA | TNS -45000VA、60000VA | 16 mm² |
SVC -25000 VA、35000 VA | TNS -75000VA、100000VA | 25 mm²以上 |
4, wiring: 1) single-phase - mark, according to the wiring respectively connected input and output line and ground.
2) three-phase - according to be marked on board, respectively, with "A" to "B", ", the letter C "terminal blocks access input phase line, marked" A "and" B ", "C" letters in the terminal access output line, marked "O", "O" of the input and output terminals access Shared center line.
Note: a: input, output line must connect line according to need and calm; B: for the sake of safety, please handle wiring all wiring thrum; C: all wiring must tighten, good contacts, or easy cause fire or burn out wire connection device.
5, check the wiring and correct, will C45 breaker handle panels to "ON" position, stabilizer immediately enter working adjustment state, work indicator, observe whether voltmeter instructions voltage stabilizer need to turn the normal (three-phase panel shift switches, observe whether normal), makes determined voltage can be connected to electric, after having confirmed.
Second, instructions
1, regulators can't long-term in corrosive gas environment.
2, the regulator is unfavorable in overload condition of long-term use of, different overload time limits see the table below:
overload(%) | Don't allow over time (points) |
20 | 60 |
40 | 30 |
60 | 5 |